Houston data center buildout is moving right along with hurricane safeguards for the roof and pad foundations for the 80,000lb generators.
Posted on 31 March 2011.
Houston data center buildout is moving right along with hurricane safeguards for the roof and pad foundations for the 80,000lb generators.
Posted in Data Center & Colocation, New Construction0 Comments
Posted on 25 March 2011.
Despite the ubiquitous AT&T/Tmobile news, “Kinetic Military Action” in Libya, and fun that some of us are missing at SxSW – a few stories might have flown under your radar this week.
Posted in "What We're Reading..."0 Comments
Posted on 23 March 2011.
The first 400-ton chiller and pumphouse arrived onsite this week. In preparation for them to reside on top of the building, engineers are enhancing the roof with additional attachments to existing steel joints.
Posted in Data Center & Colocation, New Construction0 Comments
Posted on 11 March 2011.
This week we’re laying out the conduit, which will connect the UPS power rooms to the outside generators.
Posted in New Construction0 Comments
Posted on 02 March 2011.
Construction crew digs trenches for conduit, which will house the electrical feeds connecting four 2MW generators to the A-B-C power rooms.
Posted in New Construction0 Comments